Barging.co.uk

New Build Barging

Barging.co.uk


Replica Dutch Barging.co.uk

including new build River Barge, Broad Beam and Wide Beam narrowboat style barges 


 -  Elessina - Fit-out on her mooring  -


Home - New

Build Barging


Why a New

Build  Barge?

Why New Build and not Old?

Motor or Sail?
Comparisons to a Narrowboat?
Live Aboard or Leisure

Where can wide beams cruise?
Map of UK Broadbeam Canals
Future Plans for a UK Broad Beam Network
Continental Cruising

Buying a new Barge
RCD Categorisation
Spec Check List
DIY Fit-out cost
VAT
Insurance
Barge Building Companies

Equipment Planning
Combi Inverter Comparison

Layout plans
Some new build Barge Photos
Barge Moorings

Information about the  (DBA)
Ghent 2002 DBA Rally Photos

Barge Links & Further Reading

Elessina

 Home Page

Elessina - 60ft barge -Ian & Leigh's dream  
Build Fabrication of Elessina
Elessina Fit-out at Piper Boats
Elessina Fit-out on our mooring
Latest Photos

Elessina Galley

fit-out

Elessina Master Bedroom Fit-out
Elessina Master Bathroom Fit-out
Elessina Saloon Fit-out
Elessina Electrics and Plumbing
Cruising & External Photos
Layout of Elessina
Cad Drawing Scan

Barge message board forum
Survey Questionnaire 

Our 1st project narrowboat Isabella

E-mail Ian

 

since 2nd March 2004

This page shows the fit-out of our barge Elessina. Elessina was built by Piper Boats at Stoke on Trent to a sailaway plus level, we completed the fit-out on our mooring at Port Medway Marina on the River Medway in Kent. Elessina is 60 ft long x 12'-6" wide has a 12mm thick 5ft wide flat bottom with 8/10mm thick angled side chines.  Steel construction photos the initial fit-out at Piper Boats and some cruising / external photos plus latest photos are now on separate pages. 

 


Week 1 - Thursday 15th July 2004

Our 1st day of ownership was mainly 'sea trial' and refinements. Extra ballast was installed, and now with 5mm double glazed toughened glass installed in wheelhouse (replacing the 4mm) Elessina's screen and roof raised and lowered perfectly (see video clip below). She Manoeuvres very well, turns in about a boat and a three-quarter length (without bow thruster), and reached 9.1 knots (over land speed on the gps) with a little tide assistance but in only around 1.5m deep water. I think she will probably do 9 Knots with no wind, no tide with deeper water. 

When we placed an order 18 months ago with Simon Piper, he promised us he would build us a good boat. Elessina has surpassed anything we had ever imagined we would get. For us she is absolutely perfect. Beautiful lines, well built, handles well, very spacious inside for her size, etc etc. Many thanks to Simon, Vinny and the rest of the team at Piper Boats. A beautiful 'little ship'. 

 

.......... and now the start of the hard work for us fitting out the galley, saloon, main bathroom, main bedroom and water / electrics etc.    

 


 

Lowering / Raising the wheelhouse roof (and front screen), at the touch of a button.

 

Lowering takes around 30 seconds.  Lifting around 90 seconds.

 

Window sides and rear also have to be removed / lowered to get down to around 6'-10" air draft (+/- 3" depending on the amount of fluid ballast - water, diesel, toilet waste - held in tanks). So if we have a 6'-6" bridge we may just 'scrape' through if all our tanks are full!!

 

Roof and front screen in the

 half way down position


              

Inside the wheelhouse


Week 9 (Sep-2004)

Some of the 'galley' base units in place, together with the main electrical cabinet (just visible on the left side at bottom of stairs) and main (large diameter) cables. Four 95mm2 cables have been run to the bow thruster, plus 60mm2 cables to inverter and 20mm2 to main 24v distribution panels.

Cables take a lot of time to install, especially when large holes have to be drilled through steel bulkheads, and then the cables pulled through. 


Week 13 (October 2004)

The traction batteries (12 x 2v x 920ahr) have been filled with acid. Over 100 litres in total! Not a particularly nice job (rubber apron, long rubber gloves, eye glasses and rubber boots) but job has to be done before batteries can be charged. They were 'cooking' for nearly 3 days with frequent topping up of water. The Victron Multiplus Combi was restricted to 50amp (24v) on advice from supplier for 1st charge. 1st impression of the Multiplus is very good, nice being able to connect the laptop to it to see voltage / amp inputs / outputs etc. The Multiplus is run it through a Victron Isolation transformer with auto transfer of power between shore and Electrolux generator..... It this stage it is not not tested / wired up Electrolux. But everything else has worked 1st time with no problems. We purchased the Victron Multiplus (and other equipment) from Energy Solutions, and they came along to check over the installation prior to battery charge. Good service, advice and price from Energy Solutions, if you are fitting out around the London area it would be well worth talking over your requirements with them. 

Around 60% of the electrical cables are now run. 100% (hopefully) between dc distribution board and rear cabin / wheelhouse as this area is difficult to get to now all the batteries and calorifier are installed. I do not know how many large holes have been drilled through bulkhead etc. Must be nearly 50, between 20mm and 50mm dia. The hole-saw set from screwfix at around £35 has been great, do not know what I would have done without it. I also bought a large crimping tool (up to 130mm2), and have found this invaluable. Leigh made up all the battery connecting cables, 48 (40mm2) crimps  alone, and we have run 2 x 2 x 95mm2 cables to the bow thruster. 

The one piece gas pipe from front locker storage to cooker is installed (that must have taken us 2 days to feed it through, but job done) and I particularly wanted it run in one piece. All the kitchen base units are installed (B&Q Birch wood Veneer  - 50% off in sale!!). We need to sort out worktops, sink cooker or hob / oven type etc soon.

When floating, Elessina currently lists to Starboard by around 1 degree. Probably because all the batteries (nearly 1 ton) are on the starboard side. I have tried balancing the boat using around 1.5 ton paving slabs so far, all middle to Port side - slightly towards the stern. We still have the washing machine, fridge and freezer to install on the Port side, so this will help even things up, but I think we will need another half ton of ballast on the Port side, making 2 ton in total. The barge is also high at the bow, but then we have not installed anything up front yet (master bedroom and bathroom). The theoretical ballast calculation was 1 ton towards the bow - we do not have any ballast forward of the centre of the boat!!!. We do have around 350 gal water on board at the bow and 1,000 litre of diesel (middle), but then toilet (1,000ltr) and grey (1,000ltr) tanks are empty, both of which are towards the bow, so this sort of balances out.

Annoyingly, when we are sitting on the mud we list to Port by around 1 degree. So depending upon the state of tide we list to one side or the other, making cupboard installation that bit more of a challenge!!!

 

Traction Batteries in place, 12 x 2v x 910 amp hr. They are now filled with acid, over 100 litres !! (20 gallons) and charged for 36hrs.

With 40% usable energy, 8.8Kw is available - from a normal '90% fully charged' battery bank (assuming 50% charge is flat). 

The Victron Multiplus combi (24-3000-70) in place (blue box). Now wired up to mains and ready to go. Above the Combi is the 230v mains distribution panel.

On the left side are the 4 x dc distribution panels:-

  • 12v x 3way (top),

  • 24v x 8 way lights,

  • 24v 8 way navigation

  • 24v x 12 way house (bottom). 


Week 15 (October 2004)

Luxury, we now have running water!!!.   With the help of a pump strainer, Whale high capacity pressure pump (18 l/min)  a 12 litre accumulation tank and 'Speedfit' plastic 15mm pipe, the rear wash-hand basin is now connected to the fresh water tank. It works well. No hunting, even when the tap is just open a little, although to achieve this I had to reduce the 3 bar pressure of the accumulator tank. Our previous (smaller) Whale pump with 2 litre accumulation tank always hunted with a tap partly on. 

The 1st ceiling lights (5 - in the back cabin) are now connected and working. They are gold flush mounted 24v halogen down-lighters , each with it's own built-in switch. 3 are connected to a light switch by the door, the other 2 in the bathroom are independently switched. We purchased individual lights so that we can turn on 'banks', but choose to turn then off individually, especially so when on battery power. We have 30 of these down-lighters in total.  

We are finding that it is best to have at least 2, if not 3 different jobs on the go at one time. This way, if one we can not continue working on one job, normally because we need an extra component / fitting, we can just switch to another. The alternative is to get the extra fittings, but even though the nearest B&Q and Chandlery store is only around 15 mins drive away, each trip normally takes around one hour, which can be around 20% of a days work wasted!!. Better to get these parts during the week and finish off the following weekend.

 

Elessina on her mooring at Port Medway Marina in Kent. 


Week 17 (Nov-04)

The Sanimarin toilet is installed in the back cabin. Works well, via a 3 way valve to sea or tank. All the ceiling downlighters are now working. It's nice to be able to have decent lighting to work with instead of work lights. 


Week 27 (January 2005) 

 

It's now 6 months since we took delivery of Elessina. Very little was done in the first 4 weeks because of work commitments and nothing was done during November because we took time out to visit my parents and brother in Australia.

Taking this into account, we are on schedule for the fit-out. Probably about half way fitting out the galley, half way fitting out the main bathroom and a quarter of the way fitting out the main bedroom. Overall around 40% complete. We are finding that we tend concentrate on one area at a time until something stops us (eg not having the oven / hob, or other equipment), then we move on to another area, hence overall we have done bits here and bits there.

Whenever possible we are working on the galley, but although we now have the oven and hob delivered, we are waiting to have the worktops mitred. I contemplated doing this myself, but with Richard (who is moored next to us) being a carpenter with access to a worktop jig 'volunteering' to do the work, I decided to take the easy route. Hopefully the worktops will be mitred by the end of January, then there is nothing to stop us finishing off the galley, as everything else is (hopefully) purchased / planned / sorted.

We then put a screen across the boat separating the galley & boat stern from the 'work' area, to try to limit dust and damage to completed areas. We are averaging around 20 hours work per week, around 450 work hours total to date (probably around 600 hours in total when 'homework' and 'shopping' is taken into account. I initially calculated 2,000 work hours, but this was for a normal sailaway, Elessina is a sailaway-plus, probably saving us around 750 hour's work. At this point the plan is to be around 75% complete by June, sufficient for us to start cruising / using her. 

Biggest problem encountered so far...... Trying to foresee what materials / equipment is required for the weekend ahead, and having them purchased / on board prior to a weekends work. We are only working weekends and holidays and try to organise all purchases during the week, after our 'normal' work. We are around 95% successful at this, but not having even the smallest 'required' component can curtail specific tasks from being completed. When this occurs, we move onto another task. We try very hard not to 'shop' during the weekend (to go shopping), but sometimes find we have to.

To date, all the equipment installed and tested worked 1st time and has continued to work without any problems, and we are very please with our choices. But none of the equipment has seen any heavy use as we are not living on board all of the time. The Victron Multiplus combi continues to amaze. The marina had a power outage the other weekend, only for a short period of time, but our only knowledge of it was a few 'relay clicks' within the combi, and a change of indicator lights on the front panel. We continued using all the 240v power in use at the time, it's just that the boat battery was now supplying the power. When the shore power resumed it automatically charged up the battery. 

Our mooring is bank side, chosen because we can drive right up alongside the boat to offload heavy items. Our long term plan was to try to get an outer pontoon mooring around May 2005, when most of the bulky heavy materials would be on board, and Elessina was fitted out to a 'usable' level. Outer mooring infrequently become available, so when we were advised a week ago that one was available we decided to go for it, so as soon as the tides were right (high) we moved (same marina, just different location). The outer pontoon mooring that we moved to were great, almost directly opposite to the Rochester Queen, overlooking the river and lovely open fields on the other side. We are afloat all the time.

The only disadvantage (apart from the slightly extra cost) is that we will have a longer walk from the car. We had a delivery of 12 x  8ft x 4ft ply boards over the weekend, which will (hopefully) conclude most of the 'heavy / bulky material required. We will still have some heavy items (washing machine, fridge, freezer etc), but these can be trolley'd down to the boat, and in some ways will be easier to get on board as we will be alongside a floating pontoon, whereas we currently have to use a gang plank, to bridge the gap between boat and angled bank side.

Bathroom vanity unit. The basin will be fitted to the left side unit, toilet will be installed in the space on the right.

This unit will house the hob and oven. Stair newel post now installed.

Main bathroom shower tray in place. The waste outlet fell directly over a steel cross frame, so the whole unit and already installed side panel had to be moved back towards the stern by 2".

Timber and pipe storage rack. A temporary measure to help with finding required lengths. This arrangement worked well and helped store / sort long lengths of materials

Master bedroom bed frame

Wheelhouse Instrument Panel, now with bowthruster control and a few other instruments added.


Week 28 (January 2005)

Hob and Oven are now in place, but not connected. Hopefully we will have the galley and bathroom work tops mitred this weekend, then the sink and basin can be fitted. Bathroom vanity units also now installed. We took delivery of 12 sheets of plywood over the weekend, which hopefully is the last of the ' building bulky' stuff to be carried on board.


Week 30 (February 2005)

Galley and bathroom worktop now mitred and in place, ready for us to install the sink and basin next weekend. We purchased a second 'stair' newel which we 'quartered' for installation in the bedroom at the wardrobe corner (photo shows bottom part installed against corner of bedroom wardrobe. A stair handrail and 3 spindles will be fitted, making a feature of the wardrobe side. 3 of the final 7 8x4 ply sheets have been installed under the gunnels in the saloon area.

 

Galley, with hob, oven and work tops. The back splash matches the worktops (B&Q, Ebony granite gloss). The temporary curtain to the right has been installed to try to stop dust (sawdust!) getting into the rear cabin and engine room

 

Main bedroom door. It will be teak varnished and have curtains behind the glass.

 

 

Main bathroom, with vanity units, work top and shower tray in place. The basin will be installed on the left side. Toilet on the right.

 

Lower part of quartered newel post against bedroom wardrobe corner. 


Week 32 (February 2005)

Elessina has been moved to her new pontoon mooring at Port Medway Marina.  She is now permanently afloat regardless of tides, which means when the weather improves we can take her for a cruise any time we like.

 

 

Kitchen sink unit with sink cut out and worktop mitred ready for joining.  Inside the unit is the 3 stage filter unit (left) and sink waste through hull in the centre.

Galley area from saloon a couple of weeks ago.

 

Kitchen sink now installed and worktops and matching splash backs in place. Neither sink or hob are plumbed in yet.

 

Galley area, from saloon. February 05

 

Bathroom vanity units in place, with basin cut out ready for basin to be fitted

Bathroom, now with baisn and Sanimarine toilet in place. Neither basin or loo are connected yet.


Week 34 (March 2005)

We now have cold running water to the galley sink. Most of the hot water system is also in place, but not connected yet to the rear cabin bathroom basin / shower or main bathroom basin and shower.

 

 

Elessina on her mooring at Port Medway Marina on the

River Medway in Kent, in the snow.

With the (5Kw) Bubbles diesel stove on it's lowest setting (no1) the inside temperature dropped to 8 deg C, whilst the outside was -2 deg.  The foam insulation kept snow on the roof until around about the same time as the snow on the pontoons also melted. The 'snow pattern' on the roof is the steel reinforcing. Turning up the stove had the inside temperature up to around 18 deg within a few hours. 21 deg could easily have been achieved.

 

 

Roll-front cabinet end panel shown with back cut out around pipes and barge side. This enables maximum space to be utilised, with the unit flush to the front of the gunnels..

 

The same Roll-front cabinet now finished / installed under the gunnels (left of the galley unit). The roll-front doors still have their blue plastic protection covering, they are in fact aluminium doors. The other roll-top cabinet on the right side houses the electrical distribution / controls, including the Victron multiplus inverter.

Week 38 (April 2005)

The galley is now nearly finished. We still need to get the gas connected to the oven / hob, install fridge, freezer and washer/dryer, and lay floor covering.

The main bathroom is also nearly complete. We need to install a shower drain pump out (the drain is below sea level), and connect the toilet to tank / sea via 3-way valve, and lay floor covering

We have now started on the main bedroom. All the wardrobe / cupboard doors have been ordered (from Ikea, solid beech frames, 27 doors in total), and are due for delivery mid April. They are all standard size 'kitchen'  doors. 27 seems a lot, I had not counted them until just now!!, but that is how many we need - . We have 18 doors in the kitchen. I think this number reflects the emphasis we have put on creating as much storage space as possible. We will have more cupboard space on board than in in our house, but then we have a garage loft and shed!!. We are currently building / installing the wardrobe and cupboard carcase frames, some are from Ikea 'wall' units, others from scratch using plywood.

The lounge / saloon was completed last. We found that we spend most of our 'relaxing' time - not much of that!! - in the wheelhouse, so getting the saloon ready was a low priority, it is also the workshop and main material storage department!!!.  Even in the middle of winter, when outside temperatures were zero degrees, we still found ourselves sitting in the wheelhouse. The wheelhouse is double glazed all round, but currently has no heater, although heat from the main cabin below naturally rises into the wheelhouse, and the sun warms it up very quickly, even in winter. In March we had 28 deg in the wheelhouse, when outside temperature was around 14 deg, and inside temp around 20 deg. In summer we have a number of options to keep the wheelhouse cool, we can slide the wheelhouse roof forward, or open the top half of the doors or fold down the rear screen. We found last year that the sliding roof worked best most of the time, with the doors open.

We want to start doing a little cruising in June, a few jobs remain before we can do this. The horn, navigation lights, mast spot light and VHF radio need to be wired up, plus the bow thruster live cable needs to be connected to the battery, via a 'large' isolator switch. I have the switch, but it needs to be installed and cables run to-from it.... not quite so easy when the cables are 75mm2. Also the prop-shaft needs to be covered in the engine room........

.... still lots of jobs to be done, but little by little it is all coming along quite nicely. Leigh would often remind me when we first start the fit-out that this was our home, and that the quality of the fitting and installation need to reflect that.... both the kitchen and bathroom have worked out much nicer than our home kitchen and bathroom. Both are of an equal comparable size to that in our 3-bed house. Hopefully we will soon be able to say the same with the main bedroom.

View of galley from saloon with stairs to wheelhouse on left and passageway to

rear cabin and engine room on right.

 

Galley, viewed from stairs

 

 

Galley, viewed from rear cabin / engine passageway.

 

 

 

 

 

The bathroom takes shape, top left shows 1st two 'tongue and groove' upvc facia panels in place (black marble effect), then all panels. Main photos show view from door and from above toilet. The shower waste needs to be connected to a pump out system (because the tray is lower than water level) and the toilet still needs to be connected..

Week 40 (April 2005)

Leigh spent most of the weekend mixing concrete, on board, for ballast. Around 500Kg was mixed and placed in 25Kg bags under the front port side floor. This has helped with the list, but not eliminated it entirely, but it has levelled the barge front to back (we are now just 1.5" high at the bow and 1" high at the stern compared to design drawings). We probably still need around 300Kg on the port side in the centre. Whilst Leigh was mixing concrete, I was building the master bedroom cabinets, in between helping Leigh. We now have hanging doors an all main rooms (rear cabin, bathroom and Master bedroom). These doors (from Wickes) each have 6 panes of glass, with an arched top. There will be curtains hanging behind each door, secured top and bottom, for privacy. 

 
View from Saloon into master bedroom, with bathroom door just visible on the right. Leigh's weekend work is under these floor boards!! View from master bedroom  with bedroom door and shallow (Ikea wall unit) bedroom cupboards  Master bedroom bedside cabinets under construction, with bed frame in between. Because of the bow angles, these take time to build, and are not Ikea base cupboards, although Ikea cupboards doors will be installed.

Week 42 (April 2005)

   

View into bedroom (left) and from inside the

bedroom (top), with wardrobe doors on the left

and shallow cupboards on the right.

 


Week 45 (May 2005)

     

Master bedroom wardrobes with shallow cupboard left and Newel post spindle feature on the right


Week 46 (May 2005)

      

The galley hob with newly constructed stair handrail and spindles.

A big tidy up before our 'open day'. Around 50 visitors took a look around Elessina. It was nice meeting everyone. We got the impression that everyone visiting also found it of interest. We are around 75% complete now, but intend to ease off over June - September. We will take her out cruising a few times and spend some time relaxing on board, only working on her during poor weather. The plan is to have the next 'open day' on Sunday 28th August at Chatham Dock with the DBA Rally.

There are now separate pages for Galley fit-out,   Master Bedroom Fit-out,   Master Bathroom fit-out and Electrics.


Week 47 (June 2005)

Over the past few weeks we have spent most weekends on board, staying overnight between 1 and 3 nights at a time. Work time has reduced and relaxation time increased, which is nice.

Master bedroom now has 'worktops' on all of the cupboards. The tops are left over pieces from the galley and bathroom. We put them in place, they looked good, so we thought we may as well use them. It was not planned this way!, if fact most of the work tops have been taken off the boat and were in the garage waiting to be dumped, when we realised we had sufficient remaining.

The gas oven and hob are now fully functional, having been connected to the gas supply (orange propane bottle) by Ian Britchfield of Snugglepuss. A 24v 'Pilot Gas monitoring system' has been installed, which has two remotely mounted detector heads and a remote gas switch. One of the detector heads has been installed low down in the bilges, under the oven, the other directly under the oven on the barge floor. The remote switch (solenoid valve) is installed adjacent to the gas bottle, inside the purpose built steel gas locker at the bow of the boat. The monitoring system panel is installed on the side of the oven housing, adjacent to the main entry exit doorway. At the touch of a switch on this monitoring panel we can (and will) turn on and off the gas supply at the outside gas locker. So as soon as we have finished cooking, the valve will be closed ensuring no 'live' supply to the inside of the barge. The valve also closes by default in there is no (24v) supply to it. If any one of the two sensors detect gas, the valve automatically closes. The sensor activating the alarm is identified by a light on the panel, so if we find that we are getting false alarms, we can swap the sensors around, or move the positions a little. A bubble leak tester has also been installed in the supply pipe, inside the gas locker, enabling a quick and easy check for soundness of the installation, many bubbles in the see through glass container when the red button is pressed indicates there is a leak in the system. The alarm and solenoid vale monitoring system is around £200, bubbles tester around £30. Sounds a lot, but a small price to pay for safety and peace of mind. A separate Carbon Monoxide (CO) alarm is also installed (£30 from Argos, Tesco etc.), which ensures there is sufficient oxygen levels on board.

Snugglepuss tested the pipes under pressure with air prior to filling the system with gas, then metered the pressure loss ensuring no leaks were present, and issued a test certificate. Our thanks to Ian at Snugglepuss for doing a great job.

The Bow Thruster is also now fully operational....... The Vetus 160Kgf unit (24v 7.7Kw) was mechanically installed by Piper Boats, we have run the cables and controls. The bow thruster is run off the main house batteries (we have a large battery bank) which is a 15m cable run length away. I calculated we needed 150mm2 cable size, but installed 2 x 95mm2 cables (4 cables total, 2 x red, 2 x black, giving 190mm2). Connected through a 355A fuse and a battery isolation switch (not so easy to do when the cables are so big and the connections in the engine room are not that accessible, and all power is isolated, so having to work off of torch battery lights!!). But job done. Just a touch on the rocker switch is all that is needed for the bow of the barge to respond. Very noisy inside at the bow when it operates, but normally no one will be in the bedroom whilst under way, so no problem. We ran it on and off a few times just under battery power only on our mooring (no engine or battery charge), it worked fine, taking just 1% of the battery availability power. We have a weed hatch next to the bow thruster, no leaks.

We purchased a Shoreline Fridge and a Freezer (two separate 'undercounter' units), for installation along the walkway which connects galley to rear cabin. They will have 'kitchen doors' on the fridge and freezer doors, initially we were not sure whether to fix the doors directly, or use Shorelines door kit. In the end we used the Shoreline kit, which has proved to be very good. Shorelines own energy usage figures are far better than any 'A' rated domestic fridges and freezers, better than even A+++ ratings. I will be doing a test to see how close it comes to the suppliers stated figures.


Week 48 (June 2005)

The Shoreline Fridge and Freezer are now both installed and running.  Installed side by side in the walkway connecting galley to rear cabin, they both reached recommended working temperatures within a few hours of being turned on, on the hottest day of the year.

As a point of interest, it was cooler on board inside the barge than it was inside our 10 year old home....... I can only think that much of this is down to the spray foam insulation and cream painted roof and cabin sides (the grey deck / gunnels were so hot you could not walk bare footed on them, but the cream roof was not hot). Max temp over the weekend reached inside Elessina was 28 deg. Outside was 32 deg. inside our house it was 31 deg....... Making us reconsider whether air conditioning on board is worth installing.... probably not based on this..... but will wait for the hotter weather to come!!!! 3 years later, we still see no need for an air conditioning unit.

I asked Shoreline whether a small (computer) fan would help reduce power consumption of our fridge and freezer. Their reply was that provided adequate ventilation around the back was provided an additional fan would not really do much to improve running times - except maybe in very hot weather!...... and that small computer fans take very little current but tend to make more noise than anything. They probably only need to run when the motor is running and this can be achieved by connecting across the small + & F terminals (on the rear of the unit).


  Week 50 (July 2005)

We have spent the last 10 days on Elessina, neither of us wanted to leave / return to work. We would like to move on board now, but there is still work to be done!

We fitted a VHF radio, wired up the horn and navigation lights then spent the last 7 days of our vacation cruising up and down the River Medway / relaxing. Wonderful!!! .

We moved into the master bedroom last Saturday (25th June). Its not finished (no carpet, a few wood trims missing, no handles on cupboard doors) . See photo left.

 

The bow thruster is great. Highly recommended. If you wish to do some cruising on a barge, amongst GRP and wood boats, I would say it is a must. Our biggest problem is coming back into our mooring. We have a GRP cruiser in front and a wood cruiser behind, with around 80 feet of pontoon to get into (we are 60feeet).!  First time in, I did a practice run (when the wind was only force 4) then it blew up and was gusting force 7, with a fairly strong tide. 

 

The 'working' galley (left).

No vase on board for the flowers, but a plastic measuring jug, which was used to measure the acid used to fill the batteries worked well!.

Fridge and freezer can just be seen in the centre of the photo. There is room for a washing machine to the left of the freezer. They will have matching galley doors on them....another job for later!

 No fit-out work planned on board for the summer months. Likely paint touch up the outside on a nice day, maybe fit handles to the bedroom cupboards, but not much more until the colder weather returns.

 


Week 67 (November 2005)

By the end of the Autumn cruising season , we had done around 30 cruises, 50 hours. Work resumed inside during October and we nearly completed the master bathroom, the shower is now fully operational, with the toilet just needs connecting and testing and carpet tiles to be laid.

Spent a weekend on board (Fri-to-Sun) with the outside temperature -5 deg.  With just the small (5Kw) Bubbles stove we were a cosy 21 deg in the main / forward cabin (including bathroom and main bedroom). Overnight we turned down the Bubbles stove to minimum, and it kept up a good temperature. The rear cabin and it's bathroom does remain cold, and this is where we have our only toilet and shower at the moment, hence the priority getting the main bathroom up and running.


Week 71 (December 2005)

Finishing off the bathroom and master bedroom took longer than planned. But now both 99% complete. We have laid carpet tiles in the bathroom and bedroom, and have found then to be pleasantly warm under foot, so much so that we have now laid carpet tiles in the galley area, and will likely lay them in the saloon as well. Laminate / wood floor seems very cold by comparison, and the great thing with carpet tiles is that they are very easy to lift, enabling quick easy access to bilge area storage under the floor.

We have now started on the last room, the Saloon (or workshop as it is now). Main work in the Saloon is the fitted cupboards / TV unit under the bilges and the installation of another 3/4 ton of ballast under the port saloon floor (under the fitted cupboards!!). Using any power tool on board, except drill, is just about impossible due to the amount of dust created. So everything is now being cut / planned by hand. The power tool I miss most is the Black and Decker Scorpion saw, it creates less dust than a circular saw, but still more than by hand!!!

We have spent around 1,200 hours working on board Elessina to date (equivalent to 2 x 10 hour days every week for 14 months). In practice most weekends we do around 25 hours of work (Friday pm to Sunday pm), but we have had around 5 months where we did not do any work (Nov 2004 in Australia and 4 months cruising / leisure on board Elessina during the summer of 2005) and there is always the odd day where we can not do any work, offset by bank holiday work times etc. We have had Elessina now for 17 months. I estimate another 300 hours should be sufficient to say that she is 99% complete, which will bring us into March 2006. Which is pretty much according to our timing plans. I do not think anybody could say their boat is 100% complete, as there are always a few bits to do / improve. Same as on a house. In effect I see that we will be 'complete' when 1) the saloon floor is laid (likely carpet). 2) We have working central heating (likely Webasto water). 3) We have a washing machine on-board. Lots of other jobs to complete as well as these 3, but these are the 3 key final ones.

On top of the 1,200 hours spent working on Elessina we have done around 400 hours of homework and shopping eg. Researching and buying of materials. This takes up quite a considerable amount of time, especially so when it is our first (and only) barge, but greatly assisted by the internet, especially google.


Week 74 (January 2006)

 

Over the Christmas break we installed the final 'trim' ballast under the saloon floor on the port side. 900Kg of paving slabs and 5 bags of 25Kg sand and cement. We now have a perfectly level barge, or did have until we moved some of the 'workshop' tools around, now we have a very slight list to port (we over did it!!), so may have to remove some of the ballast. But we will wait until the central heating is installed as this will predominantly be on the starboard side.

 

Now working in the saloon area, the 'workshop' has been reduced in size. TV corner units nearly done, again they are B&Q doors, with wall unit carcases.

 

We spent 8 days on Elessina over the Christmas and New Year holiday. Nice and warm inside (up to 26 deg C), cold (-5 deg C and 2" of snow) outside. Apart from the stern cabin, the whole barge could be heated with just the 5Kw Bubbles stove (diesel drip feed). Master bathroom is the warmest room on board, the Bubbles stove backs onto the bathroom, which has 'airing cupboards' around the fire place.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

                TV corner unit taking shape

                     


Week 75 (January 2006)

The saloon (see photo below) is now taking shape, looking less like a workshop every week. TV corner unit (starboard side) and shallow cupboards along the port side are now complete. A total of 18 cupboard doors (awaiting handles!!), 2 remaining uninstalled. Carpet (tile) laying has started from the bedroom door into the saloon, will continue to a couple of feet in front of the fire then stop until the 'workshop' is 'decommissioned'. Next is the 'tidying up' of the walkway utility area and central heating (will buy at the London Boat show, probably a Webasto diesel water heater).   


Week 78 (February 2006)

 

 

We have moved, onto a new pontoon, but only a few feet down stream from our previous mooring. We are now on an end mooring, making it easier to moor, although we have managed ok before. Port Medway Marina have installed a new pontoon mooring, so doubling the size of mooring capability.  There are now two separate pontoons, we are on the new one, downstream of the old. We like it very much. Less walking distance to car park and nice to be on the end of the pontoon.

 

Webasto water heater ordered, should be arriving any time now. Washing machine ordered (Hotpoint super silent washer dryer), arrives next week. Utility area in process of being tidied up - wall lighting now complete, door on fridge and freezer complete. Big tidy up of workshop tools and materials, will soon look more like a saloon than workshop!!


Week 79 (February 2006)   Cupboard doors on the fridge and freezer

Using Shorelines Integrated door kit, we now have doors on both the fridge and freezer. The doors are standard 600mm wide (B&Q) doors. Both the fridge and freezer are on a raised platform with cupboard space underneath. The fridge and freezer are just normal Shoreline appliances, not integrated ones. The washing machine fits in the gap at the end of the walkway. It is a Hotpoint Super silent Integrated washer dryer. There is enough width (600mm), but depth is tight, and I had to make a few dents into the rear cover for it to fit (not nice making dents into a brand new machine..... but it had to be done!).

 

 

 

Picture left shows the Shoreline integrated door kit. Easy to fit. Only £12 including delivery.

There is a slider fitting top and bottom connecting appliance door to wooden kitchen door. Open the outer door and the appliance door opens and closes with it.

Picture above right is taken from the rear cabin, looking forward into the galley. The fridge and freezer are on the left. Entrance to Engine room on the right (Starboard) side.

Getting the Washing machine on board was fun!!. through the roof hatch!! Actually the hardest part was lifting it up onto the roof, with 2 people it was easy to lower it down through the roof hatch.


Week 85 (March 2006)

 

The Saloon area, now with 2 seater sofa. Still surrounded by workshop equipment. The 3 seater sofa will be lowered through the roof hatch next week.

 

 

 

 

We now have the washing machine installed and up and running (behind the last door along the walkway). Super silent it certainly is. It just fitted into the space at the side of the freezer. Webasto heater now on board, ready for installation.

Notice the Australia theme above the galley door way. We have a few Ausie corners.


Week 93 (May 2006)

We are now around 98% complete. The central heating is working (just in time for summer!!), but more importantly we can have hot water without running the engine when off shore power. A few Iroko wood trims to be installed (all these need trims have be oiled / painted, we have done around 50 over the last few weeks, takes a lot of time!!). Need to install a couple more air vents (UFO type) as we are a little light on the calculated requirements, and an extraction fan in the bathroom. Also replace our temporary curtains and rug in the saloon. We intend to work until the end of May, then that will be it until November time.

Overall we are very pleased how it has turned out. Hard work but rewarding, in that we

can now relax a little and enjoy our hard work. Weather permitting we will moor off Southend over the Bank holiday weekend and watch the free Southend air show which will be directly above us, over the Thames.


Week 98 (June 2006)

Now around 99% complete, just a few small jobs to finish, which can wait until much later in the year. All vents and extraction now done. We did a few hours cruising over the first weekend in June, down to Stangate Creek where we dropped anchor overnight. Anchor and windlass worked fine with no problems, although it was only a force 2 wind. 

A quick count, and we have 105 cupboard doors / hatches on board. It was always our intention to create as much storage space as possible, and I thought we must be close to 100 doors, but not realised it was over.

 


Week 110 (September 2006).

During August we had 3 week up the Thames. It took around 10 hours from our Medway mooring to get to Teddington, with around a Force 4 wind off Southend, but everything went fine.

This photo was tTaken from the London Eye as we cruised down the R.Thames back to our mooring at Port Medway Marina. Many

thanks to Jon for emailing the photo to me. For more photos of our trip up the Thames through London click here

 


December 2006

We now have a BSS (Boat Safety Scheme) certificate. Although not necessary as we are a new build sailaway on a tidal river, all work done has been with BSS compliance in mind, so I thought it a good idea at this stage to get confirmation that we are compliant.....and we are. Main job completed over last few months is the main stairs down from wheelhouse. Piper Boats fitted a temporary stairway, which we have been using over the last couple of years. We now have broadband connection on our mooring, so all web updates now done from on board Elessina.

Christmas 2006

 

Moon rising, on our mooring at Port Medway Marina


March 2007

   

One of the last remaining jobs to be done was the main stairs down from the wheelhouse into the salon / galley. We have had temporary pine wood stairs from early on, but though practical, they did not look very good. We wanted to use the area behind the stairs for storage, but at the same time have it look tidy. Nearly every barge we have been on over the last few months we have looked for creative ideas that we could copy. In the end we decided to simply carpet over the existing. Photo above left shows 2 stairs carpeted.   Middle photo when all complete, with wicker boxes on shelves under the three lower stairs. Close up right shows how it was done, with Iroko strips down each side of the stairs covering the side carpet edge. The middle (dark) carpet is a standard width carpet tile (B&Q) so can be easily replaced when worn. We are happy with the end result, and it was a very cheap way of completing it.


March 2007

Saloon area, now completed.


February 2008

Breakfast bar added.

Fortunately the granite style worktops are still available so we were able to match existing.


    <<< Build Fabrication Photos      Home     Next Page >>> Latest Photos


 Last updated 12 July 2008