Barging.co.uk

New Build Barging

Barging.co.uk


New Build Barging.co.uk

Including Replica Dutch Barges, River Barges, Broad Beam and Wide Beam narrowboat style barges 


Kevin's 60ft Barge Project


Barge message board forum
Home - New Build Barging

Why a New Build Barge?

Why New Build and not Old?

Motor or Sail?
Comparisons to a Narrowboat?
Live Aboard or Leisure

Where can wide beams cruise?
Map of UK Broadbeam Canals
Future Plans for a UK Broad Beam Network
Continental Cruising

Buying a new Barge
RCD Categorisation
Buying a Sailaway
Spec Check List
DIY Fit-out cost
VAT
Barge Insurance Info
Barge Building Companies
Barges for Sale

DIY Fit-out
Equipment Planning
Solar & Wind Generators
Generator Sets
Useful tools for DIY fit-out
Slipping / dry docking a barge

Layout plans
Some new build Barge Photos
Barge Moorings

Information about the  (DBA)
Ghent 2002 DBA Rally Photos
Chatham DBA Rally 2005
Beale Park 2006 DBA Rally
Bell Weir Gathering 2008
Bisham Abbey 2009

Barge Links & Further Reading

Our own barge

Elessina Index

Kevins 60ft Barge Project

Ida 57ft Cruising Barge
Si and Jacq's Wide Beam
Takey Tezey
Mikes 57ft Barge Build
Mikes 57ft Narrowboat Style
Dave and Lyns 19.6m barge
Jeff & Jackies 50ft Thomas
Roger & Glynwen 55ft Barge Build

Barge message board forum
Survey Questionnaire 

Kevin won a tender for a part completed shell from the liquidator of a barge building company. The barge is 60ft x 12ft and a Nick Branson design. There is much work to be done. This is much more than a DIY fit-out. Kevin is hoping to complete in 18 month to 2 years. He has his own blog, this page will give a synopsis of the blog.

Updates; 11-Dec-09  

 29-Jan-10  

 17-Feb-10 

  14-Mar-10 

 Oct-10 

Now complete  See Kevins blog for more photos and details

http://boatbuildblog.blogspot.com/


Introduction (4-Nov-09)
We bought our first boat back in June 2006.  A 60' Narrowboat in "working" condition but only just. This boat has served its purpose in every respect and we still enjoy it. Once we got the bug for boating we started visiting the the shows. This was in hindsight not such a smart thing.  Ignorance being bliss an' all. We happened aboard a Metrofloat. My wife had to be virtually dragged of the boat!   So the seed was sown.  The problem was not having £135k to spend on a boat.  Had we, I think we would have bought it there and then.

At the same show was another exhibitor that would build a shell to any level of finish.  I was particularly impressed with the build quality and that it was a particular hull design.  Unfortunately (or fortunately depending on how you look at it) this builder went out of business before we got to placing an order.
About 18 months passed. During a forum chat I became aware of a part built shell built by the above builder.  I entered into negotiations with the forum member that had possession of the shell.  Right form the outset it was made clear to me the ownership was in legal dispute and that they would not sell it until they had full title to it.  In credit to them they could have sold it to us in dispute and not made us aware of the title problem.

After about a year waiting for the outcome of ownership I was eventually told we would have to deal with the Liquidator.   The terms of the disposal was by sealed tender. So as I am writing this I am sure you have guessed I won the tender.

Preparation and the water is on the wrong side

(11-Nov-09)

The boat is being delivered tomorrow.  I have been in the midlands where the shell is currently, since early this afternoon. 

 

As the shell has been outside for some time it has acquired about 250mm of water in the main area and  the engine bay was as full as it could be, about 450mm deep.

 

The outside of the boat is dry its fair to say the boat has no leaks :-) It took just over 4 hours to get as much of the water out as the pump would get.
 

Transportation Day (12-Nov-09)


What a stressful couple of weeks since the initial news that I'd have to bid for the boat by sealed tender.  Since winning it I have had to move fast to arrange transport, prepare the ground to receive the boat, improve the access for the truck & crane, get the power company to shroud the overhead cables and a whole host of other things like insurance. Anyway the boat is HOME. At 8am the crane arrived shortly followed by the truck.

Just over 4 hours from setting off...... The truck arrived.  Would my preparations be enough to get the truck down? If it did could the truck negotiate the bend in the middle of the drive?  As I knew the access was tight I paid extra to have a trailer with rear steering wheels.  If you look you can see them in action.  Without question had I hired a standard trailer this blog would be very reading differently right now!

So all in all a very successful day. No incidents, no accidents, no unexpected snags.  The transport was done by Streethay Wharf If you ever need to move a boat or any very long load these are the boys.  I know who I will be calling when its finished to get it out.

Nothing Obvious Done? (21-Nov-09)
There's been no obvious progress on the boat since it was delivered. I have been up to this week are sorting out the steel I need to complete the cabin.  There are 3 parts for the front that have to be profile cut.  The rest of the cabin is made from standard steel stock. Essentially the designer (link below) uses, where possible, standard steel stock sizes, if you like "off the shelf" parts.  What he does is design the bow and stern which are the complicated bits.  The middle bit of the boat is up to the builder to put in as require to the finished length or customer requirements.

"Profiling" is where the steel sheet is cut with either gas flame, plasma, laser or even water jet all controlled by computer from files supplied by the designer.  Not a lot different to cutting a dress from a pattern, indeed a paper template could me made for me to cut with a grinder.  Its the same process as used by vinyl cut lettering used by sign writers.

I have also been working on the internal layout.  This might seem very premature at the moment but its not.  Let me explain. The sides of the cabin can be supplied in one part up to 12m long but this is not cheap to do it this way as there is only one company in the UK that can do this length, also the transport from the Midlands will be expensive too, so the other alternative is to do it in shorter parts that can be folded locally which is relatively competitive due to the sizes involved.  Trouble with short lengths is there will need to be joints.  Joints will need additional work to minimise their visual impact once the boat is painted.  To minimise the the joint area will minimise the "making good".  The best way of hiding the joint is to place the windows in the joint area, that way only the small amount above and below the window require additional work.

So to find out where the windows need to go it's necessary to plan the interior.  This is the current plan (below). Measurements to come.

The blue lines are the windows the red lines are area divisions.  The length of the living space is 12.75m

I have to admit the basic plan is someone else's, but its mostly what we want so I have used this as a working example.  To make it fit our working area I have had to scale it to 60.4:1  This is accurate to 4mm over the entire length of the boat! A tolerance I can happily work with.
 

The hatched parts are builder optional

Parts I need profile cut.
The small parts are the parts to make the skeg and rudder.



Another thing  I have to consider is the roof bracing.  As I am going to use 5mm sides these will be self supporting and will not require additional vertical bracing to be welded in.  Again any welding to the sides, even inside will cause a ripple so buy using 5mm I can avoid bracing in this area. The roof bracing will be every 500mm centres.  The water tank will be bigger than this and therefore needs to be in the body before the bracing goes in.  I have been looking at the options for this.  The tank will fit under the foredeck, the dark area in the photo below.

Space for the fresh water tank. The considered options so far are, stainless steel, plastic of some sort or an older idea is to use the boat skin to form the tank making an integral tank.  The latter would give the largest capacity and the least expensive option but would require the tank the be painted with bitumen every few years so a manhole would need to be incorporated to permit access to do the repaint.  Painting the inside of the tank is a sh*t job.  I might consider this option but get it GRP'd or have a flexible liner made. 

On another note all the rain this week has started to fill up the hull.  This is actually going to be useful as the boat is about 99% level at the moment.  The water in the bottom is showing it is sitting level down its length, but about 30mm high on the port (left) side .  I need to find  some jacks to hire to make the fine adjustments and level the boat before welding starts.

I will be speaking with the designer Nick Branson early next week to pay the licence fee for the CAD files so I can get started with the steel order and so get on with the build.

At Last Some Welding Done (8-Dec-09)
Since having the boat home the weather has been either too wet or too windy or more like both.  Not the ideal conditions for MIG welding outside.

Today was different :-)  No rain and no wind.  So out came the welder this afternoon.  In about an hour or so I had welded the tops of the rubbing strakes and a weld along the top edge of the front gunwale.  The only real problem was the damp lodged behind the strakes.  As I welded this boiled off into steam and caused some problems with a smooth  flow.  Next time I will blow it out with compressed air first.
 

The hose in the picture is draining out the inside.  The pump was stopped because I needed the power for the welder, but it continued to siphon so I have just left it.  It is slow but that's OK because the pump is too fast to be efficient now.  The bottom of the boat is divide into section about 5' x 2' x 2" deep and the pump drains them quicker than new water can flow in thus the pump sucks more air than water.

I am still wondering about the best way of doing the cabin sides and roof.  The front approx. 2m is shaped and whilst I have the drawing and files to have these cut, I am considering doing it myself as I want to change the way the roof is joined to the sides.  More on that in a later blog.

I may consider buying or renting a plasma cutter and getting the steel delivered as stock sheets.  I need to have a go with a plasma cutter it think.  I am told they are very easy to use.  Failing that it will the trusty angle grinder.

I have now placed an order for the 24 curved roof bearers so things are happening at last.

Worst Of The Welding Now Done (10-Dec-09)
I have been busy welding taking advantage of the good weather.  I have done what I consider the worst part of the welding.  That being the under sides of the bottom rubbing strake.  To do this has required me lying on my back and welding on my back.  This is never fun as you WILL get burnt.

It only takes a small ball of splatter to get stuck somewhere and this is what happens.  Any welder will know exactly what I mean,  If you can wiggle about and keep it moving until it cools you usually get away with it.

I need to do some drawing tonight as I need intend to change the roof design.  The front profile pats will need to be modified to suit.  More on the roof design change in a later blog.

Welding the top of the rubbing strake



Here is one the right way up

These have been deliberately left long and will be trimmed to length later. I am keeping a spreadsheet of the weight I am adding to the hull as I need to have this so I can determine at how much ballast to add later.
 

Hmm! Curvey (11-Dec-09)


Not much done today.  I have got some revised drawings from the designer to accommodate the way I want to do the roof.

The roof beams I ordered  on Monday arrived today.

Stored on the bow for now

Updates 29th January 2010
 

Steel Arrival

The steel to complete the shell sides roof and water tank arrived today (28-Jan)
 

Now all I need is some good weather a mini-digger to lift the sheets, oh and my knee to ease up so I can get on with construction.  I went skiing last week and once again knackered my knee.  Its become an annual event over the last few years, so I have made an appointment to see a knee specialist.  I did the original injury 20 odd years ago skiing.  I'll never learn  SWIMBO says.


It doesn't look much for £2k but there is about 2 tons all cut to size and some profile cutting.
 

 
 

Updated 17-Feb-10

Put A Lid On It.!

 Well, that's exactly what we did this afternoon.

I had some adjustment to do to the front 4 roof beams this morning.  That was all I was going to do.  I wasn't happy with the line they took so after a little bit of thinking over the weekend I decided on another way of making it right.

Come 12.30 all was going well and the weather was looking very favorable so on the off chance I rung Frank to see if he was available to assist with his digger.  He was. :-)  We had already tested the lifting method last time Frank was here so I knew all would run smoothly.

As the sheets were positioned the top of the sides all started to come true.  Once all the sheets on the starboard side were tacked in place we needed true up the port side prior to tacking.  To do this the trusty ratchet straps came out again.  Starting with the first sheet it was pulled square and tacked into place, followed by the rest.  As with the starboard side as each sheet was pulled into place the top side of boat came true.  The last sheet has been left lose for now as there is a lot of trimming and shaping on this one.

A good afternoons work.  Thanks once again Frank.
 


Updated 14th March

 

Welding In More Detail

So far so I have put 11.250km of weld wire or very nearly 7 miles!!

Today I finished the port side welding (side to gunwale).

I thought I'd show in more detail the welding process from applying the weld to the final dressing. 

Its not a difficult job but it is labourious. 

12.4m again this time took 1 session and 6 hours 4 x 115mm grinding disks and 8 x 115 flap wheels. 

 

Stage 1 . Apply a good deep penetrating weld fillet

 


Stage 2. Grind back to concave with a grinding disk

 

Stage 3. Polish with the flap wheel

 

Stage 4 (right). Because I am welding outside the wind occasionally blows away the weld gas which is the flux. This causes small holes which need filling with more weld

 

Stage 5. back to stage 3


Updated October 2010

 

August 2010 - The bottom of the boat now has 2 good coats of blacking on.  That will do to hold it for the winter

 

September Partitions

September 2010. 744kg worth of paving slabs going under the bathroom floor

 

 

October 2010. Topside Cabin Cladding

 

More updates soon.

There are many, many more photos and much more info on Kevins own blog here  http://boatbuildblog.blogspot.com/


 Previous Page    Next Page >>>>  Ida - 57ft Cruising Barge


Created 12 December 2009     -     Last updated 06 April 2012